ENGINE 1.3 QUADRAJET (75PS)

19

INSTALLATION OF ENGINE ON TO THE

VEHICLE

NOTE

Before starting the installation process, check the

mounts for any wear or damage, if found replace

the mounts

1. Follow the reverse order of the removal

process to install the engine.

2.

Tighten the mounts to the specified torque

specified below.

MOUNT

BOLT / NUT

QTY

TORQUE

(Kg-m)

A Mount

M12 BOLT

3

7.8

B Mount

AM 12 NYLOC

NUT

1

10.8

C Mount

M12 BOLT

1

7.8

3. Connect all the electrical connectors, hoses,

fuel lines etc.

4. Refit all the components referring the removal

procedure.

5. Refill the lubricants, coolant; Brake fluid and

Power Steering Oil.

NOTE

It is always a good practice to trace all individual

circuits like, Cooling, Intercooler, Air intake, etc.

before starting the engine.